Construction Update #3

November 13, 2017 | Headlines

MASS+MAIN DEMOLITION : 5 buildings were demolished in the last six weeks, leaving one.

COLUMBIA ST FOUNDATIONS : steel sheeting starts this week, followed by deep piles and a concrete basement, completion expected by March 2018.

MASS AVE FOUNDATIONS : slurry wall and foundations for the 2-story below-grade garage start in December, completion scheduled for late-spring 2018.

47 BISHOP ALLEN DRIVE : footings, foundation and slab will be completed by mid-December. Wood framing will start by the end of December.