Construction Update #4

January 17, 2018 | Headlines

COLUMBIA ST FOUNDATIONS : Steel piles were completed. Foundations and basement are scheduled for completion in the Spring.

MASS AVE FOUNDATIONS : slurry wall guide walls are completed and the slurry wall box has started. Completion of the garage structure is expected by this Summer.

47 BISHOP ALLEN DRIVE : below-slab plumbing is completed. The slab-on-grade is expected by the end of January. Panelized wood framing will be erected in March. The building will be enclosed by Spring.